"In this project, the contractor faced many difficulties during construction, due to having to descend slopes, cut curves, and cross forests, hills, mountains, rivers, and streams... However, the project received support and favorable conditions from the local government regarding the construction site, and the contractors all had sufficient capacity. They worked with the spirit of 'overcoming the sun and rain,' arranging 3 shifts and 4 teams to accelerate progress when the weather was favorable," Mr. Quang shared.