TPO - Binh Duong province is spending nearly 1,400 billion VND to upgrade a 12.7km stretch of National Highway 13 (from the Binh Duong welcome gate bordering Ho Chi Minh City to Thu Dau Mot City). After more than two years, the construction unit is still "waiting" because land clearance has not been completed and the power grid relocation has not been finished.
![]() |
On August 10th, a reporter from Tien Phong newspaper observed that the project to upgrade and expand National Highway 13 in Binh Duong province has temporarily halted construction due to incomplete land clearance. In addition, the relocation of power lines remains unfinished. |
![]() |
Previously, in April 2022, the People's Committee of Binh Duong province officially commenced the project to upgrade and expand National Highway 13 from 6 to 8 lanes, spanning 12.7km. The project has an investment capital of approximately 1,400 billion VND. |
![]() |
Regarding land clearance for the upgrade and expansion project of National Highway 13, according to a report from the Department of Transport of Binh Duong province, by the end of July 2024, the section passing through Thu Dau Mot city (750m long) had been 100% handed over. |
![]() |
Meanwhile, in Thuan An city, the section from Vinh Phu welcome gate to Ong Bo bridge (4.9km) has had over 53% of the land handed over. The remaining land is expected to be handed over in Q3/2024 or may have to be extended into Q4/2024. |
![]() |
The second section, from Ong Bo Bridge to Huu Nghi intersection (2.9km long), has now achieved over 74% of the land handover, with the remaining portion expected to be handed over in the third quarter of 2024. |
![]() |
The third section, passing through Thuan An city (4.15km long), has had 88% of the land handed over, and the remaining portion is expected to be handed over this quarter. |
![]() |
In addition, the relocation of power grid infrastructure along National Highway 13 is currently underway, with the relocation of power lines in the sections from Ong Bo Bridge to Le Hong Phong intersection. |
![]() |
The Thuan An City Investment and Construction Project Management Board announced that since the beginning of August 2024, construction has begun on relocating the power grid for section 3, from Huu Nghi Street to the Le Hong Phong intersection. |
![]() |
The construction unit relocated 64 power poles along a 1,960m stretch of the route. Due to the large volume of work, the construction unit mobilized more than 175 workers and 20 cranes to complete the job. |
![]() |
According to the plan, the relocation of the entire power grid for the upgrade and expansion project of National Highway 13 section through Thuan An city will take 150 days. The relocation is expected to be completed in October. |
![]() |
In order to ensure the relocation of the power grid for the project proceeds according to the planned 150-day schedule, the authorities are urgently clearing the remaining land plots for the households. |
![]() |
To ensure the safety of people, vehicles, and construction workers during the power line relocation process, the People's Committee of Thuan An City, in coordination with the Traffic Police Department of Binh Duong Province, will assist in regulating traffic during the power outage. Becamex IDC Corporation will provide generators to ensure traffic safety. |
![]() |
National Highway 13, at the intersection near Ong Bo Bridge (Lai Thieu Ward, Thuan An City) |


Source: https://tienphong.vn/hinh-anh-duong-noi-tphcm-gan-1400-ty-dong-hon-2-nam-van-ngon-ngang-post1662592.tpo




















