This Resolution was approved by the People's Council of Hiep Duc district at the 23rd Session on March 28, 2025.
Accordingly, for Project 2, the project of Tra Nhan Village Resettlement Area (Phuoc Tra Commune) will be reduced by 425.3 million VND and an additional 326.2 million VND will be added to invest in the list of domestic electricity and lighting systems at this project.
For Sub-project 1 - Project 5, adjust down the medium-term capital plan for 2021 - 2025 of projects invested in the 2022 - 2024 period according to the approved settlement value (total capital plan reduced after settlement by VND 293.7 million).
Adjusted to reduce 118 million VND in the item of purchasing equipment for online classrooms and computers for the information room - Hiep Duc Secondary School for Ethnic Minorities and added the items of repairing and upgrading the official residence and teachers' restroom with a total investment of more than 411.7 million VND.
For Project 6, the adjustment is to reduce more than 1.1 billion VND and add nearly 2.3 billion VND to invest in the items of the Traditional Cultural Village of Ethnic Minorities in Tra Va village, Song Tra commune (phase 2).
Also at the 23rd Session, the People's Council of Hiep Duc district passed resolutions on the dismissal of the position of member of the District People's Committee; confirmed the results of the dismissal of the position of Chairman of the District People's Council and approved the termination of the duties of the 8th term District People's Council delegate (term 2021 - 2026) for Mr. Nguyen Van Tinh; approved the termination of the duties of the 8th term District People's Council delegate for Mr. Bui Hong Tinh and Mr. Vo Van Khoi.