Tu Ky disburses public investment capital quickly

With many synchronous and active solutions, Tu Ky district has been accelerating the disbursement of public investment capital.

Báo Hải DươngBáo Hải Dương28/04/2025

The 2-storey, 6-room classroom building project at Minh Duc Secondary School is expected to be put into use by the end of June 2025.
It is expected that by the end of June 2025, the 2-storey classroom building with 6 classrooms of Minh Duc Secondary School will be put into use.

Fast construction, timely disbursement

At the construction site of the 2-storey classroom building with 6 classrooms of Minh Duc Secondary School (Tu Ky), about 10 workers are urgently completing the final items to put the project into use at the end of June. The project is invested by the Tu Ky District Construction Investment Project Management Board, with a total capital of more than 5 billion VND, starting construction at the end of 2024.

According to the construction contract, the project will be completed in July. However, in order to put the project into use soon and overcome the shortage of classrooms, the investor coordinated with the construction unit to speed up the construction progress.

The representative of the construction unit said that up to now, the project has reached nearly 90% of the workload. The contractor is speeding up the progress of completing the final items such as painting walls, tiling floors, installing door systems, lighting, etc. The unit has received support from the investor such as completing procedures related to payment settlement during the construction process. Thanks to that, since the beginning of the year, the project has disbursed more than 2 billion VND, reaching 100% of the capital plan.

At the construction project of technical infrastructure for the new residential area of ​​Thuong Hai village, Binh Lang commune (phase 2), some items such as electricity, water supply, roads, sidewalks, etc. are being urgently constructed.

The contractor arranged machinery, staff and experienced workers to work continuously regardless of days off and holidays. The project has a total investment of nearly 15 billion VND, implemented in the period of 2023 - 2025, and has so far completed over 80% of the workload. The district regularly grasps, removes obstacles, and promptly disburses for each item. In April 2025 alone, the project disbursed nearly 4 billion VND, an increase of nearly 2 billion VND compared to the scenario plan.

Multiple solutions

short-story-of-the-world.jpg
Tu Ky district leaders regularly work with investors and construction units to promptly remove difficulties in implementing and disbursing public investment capital for works and projects.

Many projects and works being implemented in Tu Ky district are being accelerated by the cooperation of investors and contractors, such as the construction of classrooms at the following Primary Schools: Hung Dao (Hung Dao commune), Quang Nghiep (Dan An commune), and Tu Ky town.

All three projects have poured the roofs of the 2nd and 3rd floors. The contractor is completing the final items such as installing doors, paving the floor, etc. The construction progress is fast, so in April, the projects have disbursed nearly 3 billion VND, an increase of nearly 1 billion compared to the plan. The projects are expected to be completed and put into use in June, about 1 month ahead of schedule.

Mr. Nguyen Luong Cuong, Director of Tu Ky District Construction Investment Project Management Board, said that in 2025, the unit will be the investor of 18 projects with a total capital of about 200 billion VND. These are all projects transferred in 2025.

To date, 8 projects have been completed and 8 projects are in progress. To ensure the target of disbursing public investment capital, the Board regularly coordinates with relevant units to speed up the settlement process. Proactively resolve problems arising during the settlement process. Prepare payment records as soon as the volume is accepted.

According to the Finance and Planning Department of Tu Ky district, in 2025, the total public investment capital plan of Tu Ky district is nearly 100 billion VND. By the end of April 2025, the whole district disbursed nearly 24 billion VND, exceeding the disbursement plan by 6%; accumulated in 4 months, reaching more than 28% of the annual plan (the average disbursement rate of the province is 18%).

Compared to many other localities in the province, the public investment capital allocation plan of Tu Ky district is not high. However, with the characteristics of an agricultural district, with few projects generating resources, if there is no effort from the first days and months of the year, the disbursement will face many difficulties.

To speed up the disbursement of public investment capital, Tu Ky District People's Committee has established a working group to direct the implementation of investment projects in the district. Each member of the working group is responsible to the District People's Committee for the progress and results of each assigned project.

The district should soon develop a capital disbursement scenario for each month and quarter. Clearly identify capital needs for project categories from the time of making investment proposals to having specific plans...

short-term-investment-fund.jpg
The 2-storey classroom building with 4 rooms of Quang Nghiep Primary School (Dan An) has completed about 90% of the work volume, with the progress of disbursing public investment capital exceeding the plan.

District leaders directed investors to regularly inspect and supervise projects and works under construction. Promptly complete payment procedures and accept works when conditions are met. Actively coordinate with specialized agencies to shorten appraisal time so that new projects can start construction soon...

To have timely capital allocated to projects and works, Tu Ky district coordinated to auction land use rights in some residential areas and locations. Since the beginning of the year, the district has successfully auctioned many land lots. The retained funds have been promptly allocated to projects and works, thereby contributing to promoting the disbursement of public investment capital of the whole district.

The representative of the Finance and Planning Department of Tu Ky district said that in order to ensure the progress of disbursement of public investment capital, the district continues to review works and projects that are unable to pay, works that are temporarily suspended due to organizational restructuring, and report to competent authorities to adjust and supplement other works and projects. Increase surprise inspections of the progress of works and projects...

TRUONG HA

Source: https://baohaiduong.vn/tu-ky-giai-ngan-von-dau-tu-cong-nhanh-410377.html