Hai PhongQuang NinhHai Duong public investment disbursement is low

Báo Đầu tưBáo Đầu tư19/11/2024


Hai Phong, Quang Ninh, Hai Duong public investment disbursement is low

In the first 6 months of 2024, the disbursement rate of public investment capital in Hai Phong City and the two provinces of Quang Ninh and Hai Duong were all below the national average.

Hai Phong City People's Committee said that as of June 30, the City had only disbursed VND5,509.4 billion, equal to 32.37% of the plan assigned by the Prime Minister and 27.58% of the plan assigned by the City. The reason for the low disbursement rate was due to the preparation for bidding and difficulties in site clearance.

In 2024, with a total of more than 19,972 billion VND of public investment capital allocation plan, Hai Phong will allocate it to 3 regions. Of which, more than 9,622 billion VND will be allocated to projects directly assigned by the City People's Committee, more than 4,306 billion VND will be allocated to projects that Hai Phong decentralizes investment decisions to districts and towns, and more than 3,350 billion VND of public investment capital is an additional source of capital for the program of building model new rural communes decided for investment by the People's Committees of districts.

With a capital of more than VND 9,622 billion allocated by Hai Phong to 22 projects, new investors have disbursed over VND 2,932 billion, reaching 30.48% of the plan. Of the 22 investors assigned public investment capital in 2024, only 3 units have disbursed more than 50% of the assigned capital plan, 5 units have disbursed at a level above the average of the whole city (30.48%). Notably, among these investors, 6 units have not disbursed the assigned capital plan.

According to the assessment of the Hai Phong City People's Committee, site clearance and construction activities at some projects have not met the set progress, causing the disbursement of public investment capital in Hai Phong to be lower than the same period last year. In the coming time, the working groups urging the disbursement of public investment capital of the City need to strictly implement the instructions, ensuring the completion of the public investment disbursement plan.

For Quang Ninh province, according to the report of the Provincial People's Committee, the total public investment capital plan for 2024 of the locality is 15,130 billion VND. As of June 14, 2024, Quang Ninh has disbursed 2,351 billion VND, equivalent to 15.5% of the capital plan, and is expected to disburse 30.8% by the end of the first 6 months of the year.

As for the total provincial public investment capital of over VND 6,100 billion (accounting for 40% of the total public investment capital of the province), by the end of May 2024, only nearly VND 700 billion had been disbursed, reaching over 11% of the plan. The reasons for the slow disbursement rate of public investment capital have been pointed out by all levels and sectors, such as problems with the source of materials for leveling, reinforcing foundations, and site clearance.

Quang Ninh is striving to achieve a minimum disbursement rate of public investment capital of 80% by September 30, 2024 and 100% of the investment capital plan assigned at the beginning of the year by December 31, 2024. According to the leader of the Department of Planning and Investment of Quang Ninh, the province will accelerate the development and completion of a synchronous and modern infrastructure system, ensuring connectivity, comprehensiveness, focus and key points. At the same time, focus on implementing investment preparation for projects expected to start construction and identify a list of projects starting construction as a basis for implementing the development of the 2026-2030 medium-term public investment plan according to regulations...

Assessing the disbursement of public investment capital in 2024 of the locality, the leader of the Department of Planning and Investment of Hai Duong said that the implementation of the province's public investment plan encountered some difficulties and obstacles that need to be resolved soon. The selection of contractors for some projects is still slow, site clearance for some projects has not met the construction progress, some projects have to carry out planning and planning adjustment, so it takes a lot of time, and project investment preparation is prolonged.

As of June 30, 2024, Hai Duong has disbursed VND 1,087 billion, reaching 13% of the total capital payment plan and 17.2% of the plan assigned by the Prime Minister at the beginning of the year of VND 6,331.7 billion. Based on the implementation of projects and works, the province expects to disburse VND 8,361.6 billion for the whole year, reaching 99.7%.

Hai Duong's total public investment capital plan for 2024 is VND8,389.6 billion, including VND8,034.7 billion in domestic capital and VND354.9 billion in foreign capital. Of which, the capital plan assigned by the Prime Minister to the province is VND6,331.7 billion, the rest is additional capital.



Source: https://baodautu.vn/hai-phong-quang-ninh-hai-duong-giai-ngan-dau-tu-cong-dat-thap-d220951.html

Comment (0)

Simple Empty
No data

Same tag

Same category

The 'U-turn' of the only female student admitted directly to Ho Chi Minh City University of Medicine and Pharmacy
How does artificial intelligence work?
Ho Chi Minh City - the shape of a modern 'super city'
A series of events promises to bring Binh Dinh's image far and wide.

Same author

Heritage

Figure

Enterprise

No videos available