Urgent construction of highway through Ha Tinh before rainy season

Báo Tiền PhongBáo Tiền Phong19/11/2024


TPO - The unit implementing the North-South expressway project through Ha Tinh is taking advantage of favorable weather to reinforce the foundation and lay the first asphalt layers to make up for the progress when the rainy season comes.

Video: Speeding up on the North-South Expressway construction site through Ha Tinh. Video: Pham Truong.

Urgent construction of highway through Ha Tinh before rainy season photo 1

In August, at the construction site of the North-South Expressway through Ha Tinh, hundreds of officers, engineers, and workers from project implementing units were still working hard to ensure progress.

Urgent construction of highway through Ha Tinh before rainy season photo 2

At the construction site of the Ham Nghi - Vung Ang expressway section, one of 12 component projects of the North - South expressway in the East, phase 2021-2025, contractors are laying C25 and C19 hollow asphalt concrete layers. This section is 54.2km long with a total investment of more than VND9,700 billion, passing through Thach Ha, Cam Xuyen and Ky Anh districts of Ha Tinh province.

Urgent construction of highway through Ha Tinh before rainy season photo 3

According to the Thang Long Project Management Board (Ministry of Transport - project investor), this section has reached nearly 50% of the volume, some units have exceeded the expected progress to compensate for the upcoming rainy season.

Urgent construction of highway through Ha Tinh before rainy season photo 4Urgent construction of highway through Ha Tinh before rainy season photo 5Urgent construction of highway through Ha Tinh before rainy season photo 6

Mr. Tran An Thuyen - Deputy Commander of Joint Stock Company 471 said that the unit is joining forces with contractors to implement the 11XL package of the Ham Nghi - Vung Ang expressway section. "The weather is favorable, so the unit is focusing on machinery and human resources to urgently construct the bridge and asphalt concrete pavement items to ensure progress before the rainy season. In the rainy season, the embankment items, the access roads, and the installation of median strips can be completed," said Mr. Thuyen.

Urgent construction of highway through Ha Tinh before rainy season photo 7

Project implementation units are taking advantage of sunny days to lay layers of C25 and C19 hollow asphalt concrete.

Urgent construction of highway through Ha Tinh before rainy season photo 8

"Despite the hot weather, we still worked early to complete the assigned work, making up for the upcoming rainy days," said a highway construction worker.

Urgent construction of highway through Ha Tinh before rainy season photo 9
Urgent construction of highway through Ha Tinh before rainy season photo 10
Construction teams are mobilizing workers and machinery to speed up before the rainy season.
Urgent construction of highway through Ha Tinh before rainy season photo 11
Contractors speed up the work of filling the foundation and grading the stone.
Urgent construction of highway through Ha Tinh before rainy season photo 12

At some locations through Cam Xuyen, Thach Ha and Ky Anh districts of the Ham Nghi - Vung Ang expressway project, the 110kV, 220kV and 500kV power lines are being obstructed. In the picture is a location of a power line running across the expressway through Cam Thach commune (Cam Xuyen district).

Urgent construction of highway through Ha Tinh before rainy season photo 13

The construction unit was forced to temporarily fill the ground and "jump-frog" construction over the uncleared areas.

Urgent construction of highway through Ha Tinh before rainy season photo 14
According to the investor representative, the minimum safe height of the power line from the ground is 17m. However, when the construction is carried out, the remaining distance is 15-16m. Therefore, the machinery during the construction process will get caught in the power line and be electrocuted, so they have to choose a construction method that avoids these locations to ensure safety and keep up with the schedule.
Urgent construction of highway through Ha Tinh before rainy season photo 15

Mr. Nguyen Quang Thuc - Commander of Tu Lap Joint Stock Company said that the construction unit is from Km517+600- 521+500. "Compared to the overall progress of the whole project, the unit is ahead by about 20% and will complete the asphalt concrete paving before the rainy season. For the locations that are being monitored for subsidence, the construction will be carried out soon. For the locations that are entangled with the power grid lines, the contractor has discussed many times with the investor and the locality to soon hand over and construct the project," said Mr. Thuc.

Urgent construction of highway through Ha Tinh before rainy season photo 16
Urgent construction of highway through Ha Tinh before rainy season photo 18

To ensure the handover schedule in April 2025, each unit implementing the bidding packages is accelerating and preparing enough human resources and machinery for the project construction process.

The highway through Ha Tinh is still stuck with the power grid.
The highway through Ha Tinh is still stuck with the power grid.

Highway construction through Ha Tinh is 'winding' due to power lines, houses have not been relocated
Highway construction through Ha Tinh is 'winding' due to power lines, houses have not been relocated

Bridges across forests, rivers and lakes on the highway through Ha Tinh
Bridges across forests, rivers and lakes on the highway through Ha Tinh

Pham Truong



Source: https://tienphong.vn/cap-tap-thi-cong-cao-toc-qua-ha-tinh-truoc-mua-mua-post1662609.tpo

Comment (0)

Simple Empty
No data

Same tag

Same category

The 'U-turn' of the only female student admitted directly to Ho Chi Minh City University of Medicine and Pharmacy
How does artificial intelligence work?
Ho Chi Minh City - the shape of a modern 'super city'
A series of events promises to bring Binh Dinh's image far and wide.

Same author

Heritage

Figure

Enterprise

No videos available