Households will not receive support if they are forced to hand over their land.

Việt NamViệt Nam03/04/2025


Cam Lo district leaders said so when talking about the plan to enforce the handover of the entire construction site of the Van Ninh - Cam Lo expressway.

Regarding the remaining site clearance work in the area of ​​the overpasses of the Van Ninh - Cam Lo expressway project through Cam Lo district, the locality said that the households have basically agreed to the compensation plan and received support money. In the remaining cases, after repeated propaganda and mobilization without compliance, the district will carry out enforcement to soon hand over the entire site to the investor as planned.

Households will not receive support if they are forced to hand over their land. The expressway overpass on National Highway 9 passing through Cam Hieu commune, Cam Lo district is being urgently constructed - Photo: LT

According to the report of the Department of Construction, the Van Ninh - Cam Lo expressway section passing through the province has completed compensation, support payment and handover of the main route for 32.53/32.53 km, reaching 100% of the plan. Of which, Cam Lo district has a length of 6.58 km, Gio Linh 11.7 km and Vinh Linh district 14.25 km.

The expressway overpasses include 3 locations on National Highway 9, the northern bypass of National Highway 9 and National Highway 9D in Cam Thuy and Cam Hieu communes, Cam Lo district with a total length of 2.23 km. The land clearance in these areas has basically been completed, and households in the directly affected areas have agreed to the compensation plan and received full support money.

Households will not receive support if they are forced to hand over their land. Households in Nam Hieu village, Cam Hieu commune, Cam Lo district receive support money to hand over the construction site of Van Ninh - Cam Lo expressway - Photo: LT

According to the leader of Cam Lo District People's Committee, there are still some households eligible for compensation and support but located on the service road, the section is far from the overpasses, and has little impact on the construction of the Van Ninh - Cam Lo expressway project. The locality is actively mobilizing and persuading them to receive support money and hand over the site. In case the households still do not cooperate, the locality will enforce and protect the construction. However, this is the last resort because if forced, the households will not receive any support regime.

Households will not receive support if they are forced to hand over their land. The Van Ninh - Cam Lo expressway project passing through Quang Tri and Quang Binh provinces has completed 59 km/62.32 km - Photo: LT

According to information from the Ho Chi Minh Road Project Management Board, up to now, the Van Ninh - Cam Lo expressway project passing through Quang Tri and Quang Binh provinces has completed 59 km/62.32 km. Of which, the road foundation has been completed for 55.62 km/62.32 km, construction of 29/29 bridges has been implemented and girders have been installed on 23/29 bridges. For the remaining volume, the units are striving to basically complete it by April 30, 2025, and the 3 overpasses are striving to be completed by June 30, 2025.

Le Truong



Source: https://baoquangtri.vn/cac-ho-gia-dinh-se-khong-duoc-nhan-che-do-ho-tro-neu-bi-cuong-che-ban-giao-mat-bang-192688.htm

Comment (0)

Simple Empty
No data

Same tag

Same category

Ho Chi Minh City is bustling with preparations for the "national reunification day"
Ho Chi Minh City after national reunification
10,500 drones show in Ho Chi Minh City sky
April 30 Parade: City view from helicopter squadron

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product