Chairman of the Provincial People's Committee Vuong Quoc Tuan inspected the site clearance work of the Ring Road 4 project - Capital Region

On the morning of April 13, Comrade Vuong Quoc Tuan, Alternate Member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee inspected the progress of site clearance for the Ring Road 4 project - Hanoi Capital Region, the section passing through Bac Ninh province. Accompanying him was Comrade Ngo Tan Phuong, Vice Chairman of the Provincial People's Committee.

Báo Bắc NinhBáo Bắc Ninh13/04/2025

Chairman of the Provincial People's Committee Vuong Quoc Tuan inspected the ground in Khac Niem ward (Bac Ninh city).

According to the report of the investor, the Management Board of Transport and Agriculture Projects, the Ring Road 4 project, the section passing through the province, has approved the compensation plan, land acquisition of 370.055/374.0 ha (land area within the 90m boundary), reaching 98.945%; the remaining 3.945 ha, accounting for 1.055% of the residential land area and land allocated without authority has not been completed. Specifically: Bac Ninh city has 190 households with residential land area, land allocated for sale without authority that must be recovered, currently has approved the compensation plan for 107/190 households; Que Vo town has 102 households, has approved the compensation plan for 32/102 households; Thuan Thanh town has 126 households, has approved the compensation and support plan. Electricity, water and irrigation infrastructure items are striving to be relocated in September. Localities are urgently completing resettlement areas to soon hand over land to people whose land has been recovered, stabilizing their lives.

People dismantled the project and returned the site to the investor.

Up to now, the construction progress of packages 14, 15, 16 is being vigorously implemented. However, packages 15 and 16 have not met the schedule due to problems with the land area for residential use and land for sale without authority; the construction capacity of some contractors has not met the requirements; it is necessary to increase machinery and equipment, especially rollers, bulldozers and levelers. Package 14 in particular is about 3 months ahead of schedule, and is currently paving concrete layers. The total construction value of the entire project is 740.50 billion VND / 2,299.0 billion VND, accounting for 31.0% of the volume value.

Chairman of the Provincial People's Committee Vuong Quoc Tuan directed Thuan Thanh town to quickly return the site to the investor.

Directly inspecting the land acquisition and clearance work for residential land and land sold without authority in Khac Niem and Hap Linh wards (Bac Ninh city), Chi Lang commune (Que Vo town), Mao Dien commune (Thuan Thanh town), Chairman of the Provincial People's Committee Vuong Quoc Tuan highly appreciated the spirit of urgent, drastic and responsible participation in propaganda, mobilization and dialogue of the Party committees and authorities of localities where the project passes through regarding the land acquisition and clearance work, creating high consensus among the people. The Chairman of the Provincial People's Committee requested Bac Ninh city, Que Vo town and Thuan Thanh town to seamlessly hand over the site to the investor before April 22. At the same time, he requested Que Vo town to participate more resolutely; develop a detailed plan, clear completion schedule, and have frank dialogue with the people in compensation and support for the recovered land; Develop a plan to protect construction and speed up the construction progress of resettlement areas, ensure people's safety, create a spillover effect, and convey messages to localities where Ring Road 4 passes through.

Chairman of the Provincial People's Committee Vuong Quoc Tuan responded to a number of petitions from people in Chi Lang commune (Que Vo town) whose residential land was confiscated.

The Chairman of the Provincial People's Committee requested the Management Board of Transport and Agriculture Projects, immediately after receiving the site, to direct and urge contractors to speed up the construction progress in accordance with the spirit of 3 shifts, 4 teams, ensuring quality, technique and aesthetics; strictly handle contractors who do not have the capacity to construct according to regulations, determined to complete the Ring Road 4 project on schedule.

Hoai Anh

Source: https://baobacninh.com.vn/web/bbn/news/-/details/20182/chu-cich-ubnd-tinh-vuong-quoc-tuan-kiem-tra-cong-tac-giai-phong-mat-bang-du-an-uong-vanh-ai-4-vung-thu-o