TPO - After more than 6 months of implementation, the National Exhibition Center project in Dong Anh district (Hanoi) is gradually taking shape. Construction units are actively implementing foundation items, ancillary buildings, fences, tree planting, landscapes, etc. The project is expected to be completed in July 2025, on the occasion of the 80th anniversary of National Day (September 2, 1945 - September 2, 2025).
TPO - After more than 6 months of implementation, the National Exhibition Center project in Dong Anh district (Hanoi) is gradually taking shape. Construction units are actively implementing foundation items, ancillary buildings, fences, tree planting, landscapes, etc. The project is expected to be completed in July 2025, on the occasion of the 80th anniversary of National Day (September 2, 1945 - September 2, 2025).
The panorama of the National Exhibition and Fair Center worth more than 7,000 billion VND is gradually taking shape. |
Started on August 30, 2024, the National Exhibition and Fair Center is considered a key project of Hanoi Capital. |
The project has a scale of 90 hectares, is in the Top 10 largest exhibition centers in the world and is one of the key international projects, playing an important role in promoting the socio-economic development of Hanoi city and the North Red River region. |
The indoor exhibition area stands out with a design inspired by the Golden Turtle God - the god associated with the legend of the construction of Co Loa citadel. Currently, the construction unit's machinery and human resources are actively implementing the foundation, ancillary buildings, fences, tree planting, landscape... The project is expected to be completed in July 2025, to celebrate the 80th anniversary of National Day (September 2, 1945 - September 2, 2025). |
The center includes an indoor exhibition building with the image of the Golden Turtle God with 9 sub-areas with a total area of over 130,000m2, 4 outdoor exhibition parks with a total scale of up to 20.6ha, 2 other small-scale indoor exhibition houses and various auxiliary works... |
The project is located right at the Northeast gateway of Hanoi, the center of important traffic arteries to the provinces including planned roads, airways and metro. |
At present, the construction unit is actively and uniformly implementing all items of the project. |
In addition to focusing on assembling the steel frame structure of the main building, machinery and human resources also carry out the construction of the roadbed, auxiliary items, fences, tree planting, landscape, sidewalk paving and auxiliary works around the area... |
When completed and put into operation, the National Exhibition and Fair Center will be a new symbol of development for the Capital, contributing to making Hanoi an "exhibition capital" of the world. |
3D perspective of the project, after completion, the National Exhibition and Fair Center will be the destination for global-scale trade events and exhibitions. |
Source: https://tienphong.vn/trung-tam-hoi-cho-trien-lam-quoc-gia-hon-7000-ty-dong-dan-lo-hinh-hai-post1722960.tpo