There are still 3 high voltage power line locations that have not been relocated for the construction of the Bien Hoa - Vung Tau Expressway Project.

(DN) - The Department of Construction has just issued Notice No. 34/TB-Sxd dated July 24 on the results of inspection and supervision of the construction progress of Component 1 of the Bien Hoa - Vung Tau Expressway Project. The inspection team of the Department of Construction and related units noted that there are still 3 high-voltage power lines in the project area that have not been relocated.

Báo Đồng NaiBáo Đồng Nai27/07/2025

Construction of the intersection between Bien Hoa - Vung Tau Expressway and Vo Nguyen Giap Street. Photo: Pham Tung
Construction of the intersection between Bien Hoa - Vung Tau Expressway and Vo Nguyen Giap Street. Photo: Pham Tung

Specifically, there are currently 2 locations that have not been relocated at the intersection between Bien Hoa - Vung Tau Expressway and Vo Nguyen Giap Street, causing difficulties in the construction of the intersection approach road. Along with that, 1 location that has not been relocated at Km4+443 on Ham Nghi Street is causing difficulties in the construction of the approach road to the overpass.

Therefore, the Department of Construction requests that the project investor, the Provincial Construction Investment Project Management Board, work with the Provincial Land Fund Development Center, the Regional Project Management Board 5 and related units to urgently relocate technical infrastructure works, including high-voltage power lines within the project's construction scope so that the contractors' construction work can be synchronized.

To ensure the project's construction progress, the Department of Construction requests contractors to proactively develop a specific construction material supply plan for each day and each stage to meet the requirements for construction progress of each project item. In case of difficulties or problems, contractors are requested to summarize and report to the investor for consideration and proposal to competent authorities for handling.

The Department of Construction assessed that the recent heavy rains have led to the gathering of materials (filling soil, rocks of all kinds, etc.) not meeting the requirements, causing delays in the construction progress according to the signed contract. The Department of Construction requested the investor to request contractors to adjust the detailed construction schedule based on the actual situation of the construction site, supply of materials, equipment, and human resources. In particular, the volume of materials supplied each day, equipment, and human resources for each specific work item must be clearly shown and sent to the Department of Construction.

Pham Tung

Source: https://baodongnai.com.vn/tin-moi/202507/con-3-vi-tri-duong-dien-cao-the-chua-di-doi-de-thi-cong-du-an-duong-cao-toc-bien-hoa-vung-tau-85b03e8/


Comment (0)

Simple Empty
No data
Overview of the first A80 training session at Ba Dinh Square
Lang Son expands international cooperation in preserving cultural heritage
Patriotism in the young way
People joyfully welcome the 80th anniversary of National Day
Vietnam women's team beat Thailand to win bronze medal: Hai Yen, Huynh Nhu, Bich Thuy shine
People flock to Hanoi, immersing themselves in the heroic atmosphere before National Day.
Suggested locations to watch the parade on National Day September 2
Visit Nha Xa silk village
See beautiful photos taken by flycam by photographer Hoang Le Giang
When young people tell patriotic stories through fashion

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product