Vietnam.vn - Nền tảng quảng bá Việt Nam

Độc lập - Tự do - Hạnh phúc

[Photo] Mobilizing all resources to complete the 500kV Lao Cai-Vinh Yen Line

With the spirit of solidarity and a common goal, the construction forces at the construction site of the Lao Cai-Vinh Yen 500kV Transmission Line Project are striving to overcome all difficulties, focusing all resources, accelerating to bring the Project to the finish line on schedule, ensuring the quality of the project and technical and aesthetic requirements.

Báo Nhân dânBáo Nhân dân11/08/2025

The Lao Cai - Vinh Yen 500kV Transmission Line Project (Project) is a national key energy project, assigned by the Prime Minister to Vietnam Electricity Group (EVN) as the investor, Power Project Management Board 1 (EVNPMB1) as the investor representative, with the goal of enhancing the safe and stable operation of the national power system, releasing the capacity of hydropower plants in the Northwest region and neighboring provinces.

The project has a total investment of more than 7,410 billion VND, starting at Lao Cai 500kV Transformer Station (TSS) and ending at Vinh Yen 500kV Transformer Station (TSS). The project passes through 31 communes in Lao Cai and Phu Tho provinces with a total length of 229.5km and 462 column foundation locations. Currently, the construction sites are being urgently implemented.

As of August 11, the pole erection work has been completed at 326/468 pole positions (69.66%), 141/468 positions (30.13%) are being transported, assembled and erected; 28/242 anchor intervals (11.57%) have been completed, 37/242 anchor intervals (15.29%) are being pulled, and 177/242 anchor intervals (73.14%) have not yet been constructed.

vt404-completed-in-process-of-glue-installation.jpg

VT404 column location has been completed and the wire pulling project is underway.

check-day.jpg

Check the wire before pulling the wire at location VT404.

check-machine-hammer.jpg

Workers operate the wire pulling machine to serve the wire pulling process at column VT404.

drone-check.jpg

Checking drone to spread bait wire for wire pulling construction at VT404 column location.

vt-369.jpg

Location of pole VT369 - one of two poles crossing Lo River (along with pole VT370), located in Dan Chu commune (Phu Tho province), 130m high, weighing 360 tons, has been completed and is preparing for wire pulling.

check-369.jpg

VT369 column location is under construction to prepare for wire pulling.

369.jpg

Location 369 is currently performing work such as installing insulators, construction scaffolding... to prepare for wire pulling.

The project has a large construction volume, short construction time, mountainous terrain, high and rugged terrain, especially, the weather in the months of May, June and July (peak construction months) in Lao Cai and Phu Tho provinces often had intense heat, heavy rain, thunderstorms, causing construction work to be temporarily suspended to ensure safety and overcome the effects of storms.

In addition, the contractor's workforce was not sufficient to meet the project's needs under the conditions of high construction intensity, short time and simultaneous implementation of many tasks. EVN mobilized additional support forces from units in the industry with nearly 1,000 officers and employees, from Military Region 2 with more than 200 officers, soldiers and a number of youth union members.

Currently, workers and support forces are working hard day and night to urgently construct the 500kV Lao Cai-Vinh Yen transmission line.

ptc3laocaivinhyen-4-20250806220407988.jpg

Gia Lai Power Transmission Team, Power Transmission Company 3 (PTC3) participated in supporting the Project with the spirit of "No matter how hard it is, as long as it meets the schedule". (Photo: PTC3)

img-2943.jpg

Officers and soldiers of Military Region 2 are contributing to speed up the construction progress of the 500kV Lao Cai-Vinh Yen Transmission Line.

LE CHI

Source: https://nhandan.vn/anh-huy-dong-moi-nguon-luc-de-hoan-thanh-duong-day-500kv-lao-cai-vinh-yen-post899922.html


Comment (0)

Simple Empty
No data
Patriotism in the young way
People joyfully welcome the 80th anniversary of National Day
Vietnam women's team beat Thailand to win bronze medal: Hai Yen, Huynh Nhu, Bich Thuy shine
People flock to Hanoi, immersing themselves in the heroic atmosphere before National Day.
Suggested locations to watch the parade on National Day September 2
Visit Nha Xa silk village
See beautiful photos taken by flycam by photographer Hoang Le Giang
When young people tell patriotic stories through fashion
More than 8,800 volunteers in the capital are ready to contribute to the A80 festival.
The moment the SU-30MK2 "cuts the wind", air gathers on the back of the wings like white clouds

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product