In 2024, the total adjusted investment capital plan of Duy Xuyen district is nearly 216.3 billion VND (not including the 2023 capital allowed to be extended). However, according to the aggregated data, in the first quarter of this year, the district has only disbursed more than 7 billion VND, reaching 3.26%.
According to the leader of Duy Xuyen district, the reason for the slow disbursement of investment capital is that compensation and resettlement policies change frequently, making it difficult to carry out site clearance work.
Meanwhile, recently, soil, sand and stone for construction in the area have been very scarce; the implementation of bidding has been slow...