Construction across the festival on the Dong Dang-Tra Linh highway construction site

NDO - These days, everyone is jubilant, excited, and happy during the important national holiday of April 30. At the construction site of the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway project, more than 3,000 engineers and workers are still working hard, speeding up the progress, aiming to open the entire expressway in December 2025.

Báo Nhân dânBáo Nhân dân01/05/2025

Mr. Nguyen Duc Tuan, Deputy General Director of Dong Dang-Tra Linh Expressway Joint Stock Company, shared that with the spirit of working "throughout holidays and Tet", during the April 30 and May 1 holidays this year, construction units mobilized more than 3,000 personnel and 1,291 machines and equipment to simultaneously carry out construction of roadbed excavation, overpasses, tunnels through mountains and drainage culverts...

At the Dong Khe road tunnel project, after completing the excavation and lowering stage, workers are focusing on installing concrete formwork for the tunnel lining, constructing drainage ditches and electrical systems.

Mr. Nguyen Xuan Thanh, the shift leader of the Dong Khe tunnel project, said that the team still maintained an urgent working pace during the holidays because the workload ahead is still very large and we are striving to complete the construction progress ahead of the Dong Khe road tunnel construction plan.

Construction across the festival on the Dong Dang-Tra Linh highway construction site, photo 2

Construction of road tunnel on Dong Dang-Tra Linh expressway.

Passing through Lang Son and Cao Bang provinces, the Dong Dang-Tra Linh expressway project has a total length of 121km, divided into 2 investment phases. Phase 1 is invested with a length of more than 93.35km, with a roadbed of 17m. The total investment is 14,114 billion VND.

Currently, the contractors have been handed over 93.14/93.35km of construction site by the locality, equal to 99% of the project's construction site.

To date, the construction output of the Dong Dang-Tra Linh Expressway project has reached VND2,409/10,438 billion (capital 2025), equal to 23% of the plan. Contractors are striving to speed up the construction progress, and open the project phase 1 in December 2025 and are ready to start the project phase 2 on September 2.

Contractors said the challenge was the amount of work that had to be completed in a short period of time (less than 8 months), forcing contractors to recruit additional workers. Meanwhile, attracting drivers and machine operators to work the night shift at the project was not easy, directly affecting the overall progress of the project.

In order to solve the problem of construction human resources for contractors, Deo Ca Group has worked with the Central College of Transport 1 and Central College of Transport 4 to "order" additional human resources for drivers and machine operators from these training facilities for construction units.

With many synchronous solutions implemented, it is expected that the Dong Dang-Tra Linh Expressway project phase 1 will be completed on schedule, with the target of opening the route in December 2025, aiming to put it into operation in 2026.

Source: https://nhandan.vn/thi-cong-xuyen-le-tren-cong-truong-cao-toc-dong-dang-tra-linh-post876687.html


Comment (0)

Simple Empty
No data

Heritage

Figure

Business

No videos available

News

Political System

Local

Product