Tang Long Bridge Construction, Investor Repairs Damaged Nearby Infrastructure

Báo Giao thôngBáo Giao thông29/09/2024


On September 29, the representative of the HCM City Traffic Construction Investment Project Management Board (Traffic Board) said that the damage on La Xuan Oai and Lo Lu roads due to the impact of the Tang Long bridge construction area has been repaired.

Previously, from around the beginning of September, due to the impact of prolonged rain for many days, the existing La Xuan Oai road did not have a drainage system, leading to stagnant water causing damage to the road surface.

Specifically, the sidewalk of La Xuan Oai from the intersection of D2 High-Tech Park Road to Tang Long Bridge has deep holes, the asphalt concrete road surface is damaged, causing unsafety.

Thi công cầu Tăng Long, chủ đầu tư khắc phục hư hỏng hạ tầng lân cận- Ảnh 1.

The road surface is full of potholes and gutters due to the impact of the construction of Tang Long Bridge. (Photo: Dung Nhi)

In addition, from Lo Lu intersection to Tang Long bridge, construction vehicles carrying materials in and out have dropped soil, causing the road surface to be flooded.

In addition, at the intersection of La Xuan Oai - Lo Lu, the construction unit pumped water onto the existing road surface, causing frequent congestion during rush hour.

Many people have expressed their anger to the Thu Duc City Technical Infrastructure Development Center about the above situation.

The Traffic Department said that when the incident was discovered, they patched it with stones but could not lay asphalt due to continuous heavy rain, resulting in the road surface not meeting operating requirements.

Currently, the Traffic Department has paved the road surface with asphalt concrete to ensure safety.

In addition, for the area from Vo Nguyen Giap Street to Tang Long Bridge, the Traffic Committee has requested the Ho Chi Minh City Department of Transport to approve traffic organization for vehicles to move to the new road section to close the old road to serve the construction of the left branch road at the beginning of the bridge.

For the culvert location across Lo Lu intersection, because the intersection is the lowest elevation, the amount of water on Lo Lu street accumulates, causing sand and soil to accumulate. The Traffic Department has dug a temporary ditch to drain the water and completely restore the road surface.

Thi công cầu Tăng Long, chủ đầu tư khắc phục hư hỏng hạ tầng lân cận- Ảnh 2.

Ho Chi Minh City Department of Transport has repaired the damage during the construction of Tang Long Bridge.

Tang Long Bridge across Trau Trau canal is 231m long, including 2 branches, each branch has 2 lanes and a sidewalk. The project started in late 2017 with a total investment of more than 740 billion VND.

In September 2019, the project had to be suspended due to land issues. The project was not restarted until the end of October 2023.

According to the expected schedule, the left branch bridge will be completed and opened to traffic by December 2024, then the old bridge will be dismantled and the right branch bridge will be constructed.

The project is expected to be completed in December 2025. Currently, the construction units are closely following the progress, the work of casting beams and producing bridge bearings has been completed and the installation of beams will be organized in October 2024.



Source: https://www.baogiaothong.vn/thi-cong-cau-tang-long-chu-dau-tu-khac-phuc-hu-hong-ha-tang-lan-can-192240929134818154.htm

Comment (0)

Simple Empty
No data

Same tag

Same category

Fireworks filled the sky to celebrate 50 years of national reunification
50 years of national reunification: The checkered scarf - the immortal symbol of the Southern people
The moment the helicopter squadrons took off
Ho Chi Minh City is bustling with preparations for the "national reunification day"

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product