The leaders of Dong Nai province received and participated in the working delegation with the Provincial Party Committee member, Vice Chairman of the Provincial People's Committee Ho Van Ha; Member of the Provincial Party Standing Committee, Party Committee Secretary, Chairman of the People's Council of Long Thanh commune Duong Minh Dung.
Party Central Committee member and Vice Chairman of the National Assembly Vu Hong Thanh talks with ACV representatives at the construction site of the Long Thanh Airport passenger terminal. Photo: Pham Tung |
Reporting to the National Assembly delegation, Mr. Nguyen Tien Viet, Deputy General Director of Vietnam Airports Corporation (ACV), said: Currently, all project packages are being constructed simultaneously on the entire construction site in the spirit of "overcoming the sun, overcoming the rain, not losing to the wind and storm", "3 shifts, 4 crews", construction "through holidays, through Tet, through days off".
Provincial Party Committee member, Vice Chairman of Dong Nai Provincial People's Committee Ho Van Ha discussed with the working delegation on runway number 1 of Long Thanh Airport. Photo: Pham Tung |
In the bidding packages, the consortium of contractors mobilized hundreds of construction teams with nearly 14,000 experts, engineers, workers, and about 3,000 construction equipment to speed up the progress with the basic goal of completing the project before December 19, 2025, putting it into operation and commercial exploitation in the first half of 2026 as required by the Prime Minister .
To date, the total project implementation volume has reached more than 52.5% of the contract value, the overall progress is following the plan. In particular, many important packages are committed to shortening the progress by 3-6 months compared to the original contract, demonstrating the high determination of the investor and contractors.
Member of the Party Central Committee, Vice Chairman of the National Assembly Vu Hong Thanh surveyed the construction of the passenger terminal of Long Thanh Airport. Photo: Pham Tung |
Faced with the weather challenge of this year's early and prolonged rainy season, directly affecting underground items such as tunnels, drainage systems, and roadbeds, ACV has proactively adjusted construction methods, increased manpower and machinery, and made the most of sunny days to make up for the delayed progress.
ACV representative reports to the working group on the construction progress of runway 2. Photo: Pham Tung |
Regarding the construction of runway No. 2, ACV representative said: The project will start construction at the end of May 2025 and is expected to be basically completed in sync with the entire project. Currently, at the construction site, the joint venture contractor is simultaneously implementing many construction steps for the foundation, foundation, and drainage system.
For the passenger terminal project, more than 95% of the rough construction work has been completed. The central steel roof has reached its completion level since April 2025. The roofing system, skylight, glass wall, MEP (electricity, water, air conditioning) are being deployed simultaneously. The goal is to complete the construction and architecture before December 19, 2025 for technical flights, and hand over the site for equipment installation from the end of 2025.
Member of the Party Central Committee, Vice Chairman of the National Assembly Vu Hong Thanh surveyed the construction site of Long Thanh Airport Project. Photo: Pham Tung |
Speaking at the project site, Vice Chairman of the National Assembly Vu Hong Thanh assessed: Currently, the construction items of the Long Thanh Airport Project have clearly taken shape. Emphasizing the need to ensure the basic progress requirements to complete the project before December 19, 2025, Vice Chairman of the National Assembly Vu Hong Thanh requested that investors and contractors make more efforts to speed up the progress of the items, while ensuring the quality of the project.
"We must do it quickly, do it well and ensure quality" - Vice Chairman of the National Assembly Vu Hong Thanh suggested.
Member of the Party Central Committee, Vice Chairman of the National Assembly Vu Hong Thanh presented gifts to encourage investors and construction units of Long Thanh Airport. Photo: Pham Tung |
Also at the project site inspection, Vice Chairman of the National Assembly Vu Hong Thanh presented gifts and encouraged the investor and contractors of the Long Thanh Airport Project.
Pham Tung
Source: https://baodongnai.com.vn/tin-moi/202508/pho-chu-tich-quoc-hoi-vu-hong-thanh-san-bay-long-thanh-phai-lam-nhanh-va-dam-bao-chat-luong-3d60727/