Complete installation of 168 girders of 14 spans of Thong Nhat Bridge in August 2025

(DN) - On July 25, Mr. Nguyen Linh, Deputy Director of the Provincial Construction Investment Project Management Board, said that the construction and installation of girders of the Thong Nhat Bridge spans under the Bien Hoa City Central Axis Road Project is expected to be completed in August 2025.

Báo Đồng NaiBáo Đồng Nai25/07/2025

The construction of the girder installation of the Thong Nhat Bridge spans is expected to be completed in August 2025. Photo: Pham Tung

After completing the bridge girder construction, contractors will pour the bridge deck and complete other items.

According to Mr. Tran Hoang Nam, Director of the Project Management Board (under Mekong Construction Investment Joint Stock Company No. 1), for the entire Thong Nhat Bridge project, contractors will have to install 168 girders of 14 bridge spans. Currently, contractors have completed the installation of girders of 9 bridge spans. The remaining bridge spans will have their girders installed in August 2025.

Regarding the completion of all construction items of Thong Nhat Bridge, Mr. Tran Hoang Nam said that after completing the construction of the girder, the bridge deck will be poured. The completion of the entire Thong Nhat Bridge depends on the progress of the site handover, because currently, the construction site of the approach road has not been fully handed over.

The Bien Hoa City Central Road Construction Investment Project is over 5.4 km long, starting at the intersection with Vo Thi Sau Street and ending at the intersection with Dang Van Tron Street (at the An Hao Bridge intersection). The project has a total investment of about 1.5 trillion VND. Of which, package 11 - construction of Thong Nhat Bridge, access roads at both ends of the bridge and ensuring road traffic safety during the project construction process is worth over 479 billion VND.

According to the design, Thong Nhat Bridge has a scale of 6-10 lanes, a width of 45-95m, a length of about 765m, of which the main bridge is 559m long. The project started construction in early 2023, however, the construction progress has been continuously delayed due to problems in site clearance.

Pham Tung

Source: https://baodongnai.com.vn/kinh-te/202507/hoan-thanh-lao-lap-168-dam-cua-14-nhip-cau-thong-nhat-trong-thang-8-2025-c7305ea/


Comment (0)

Simple Empty
No data
Patriotism in the young way
People joyfully welcome the 80th anniversary of National Day
Vietnam women's team beat Thailand to win bronze medal: Hai Yen, Huynh Nhu, Bich Thuy shine
People flock to Hanoi, immersing themselves in the heroic atmosphere before National Day.
Suggested locations to watch the parade on National Day September 2
Visit Nha Xa silk village
See beautiful photos taken by flycam by photographer Hoang Le Giang
When young people tell patriotic stories through fashion
More than 8,800 volunteers in the capital are ready to contribute to the A80 festival.
The moment the SU-30MK2 "cuts the wind", air gathers on the back of the wings like white clouds

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product