Why does Quang Ngai not continue to invest in phase 2 of the National Highway 1A Bypass Project?

Báo Đầu tưBáo Đầu tư01/05/2024


Why does Quang Ngai not continue to invest in phase 2 of the National Highway 1A Bypass Project?

Because the toll revenue of phase I is not guaranteed, Quang Ngai province cannot work with the BOT investor to expand the National Highway 1A bypass project through Duc Pho town during this period.

According to the feedback of voters of Pho Vinh ward, Duc Pho town, Quang Ngai province, the National Highway 1A bypass project in Duc Pho town has 4 lanes and is divided into 2 construction phases. Phase 1 has been constructed and put into use 2 lanes, and is collecting BOT fees. However, the investor has not yet started construction of phase 2. Voters of Pho Vinh ward, Duc Pho town request the Provincial People's Committee to pay attention and give direction.

Responding to this issue, the People's Committee of Quang Ngai province said that according to the financial plan of the two BOT contracts: BOT Duc Pho and BOT expansion of National Highway 1A, the toll revenue at Tu Nghia Toll Station is used to repay the capital for the two BOT Duc Pho and BOT Quang Ngai projects (Thien Tan BOT Company Limited).

However, since the National Highway 1A Expansion Project came into operation, due to the impact of the economy, the traffic volume through the station has decreased, the fee reduction for people near the station has been implemented, the impact of the Covid-19 pandemic has been felt, etc., leading to a significant decrease in the actual revenue of the Project due to the financial plan, which does not ensure the debt repayment capacity of the 2 Projects. Currently, the monthly revenue is not enough to pay the principal and interest of the bank, only enough to pay the interest on the loan. Therefore, up to now, the Project has not been balanced and the capital has not been recovered.

Due to the above difficulties, the Department of Transport, in coordination with the BOT enterprise, reported to the Vietnam Road Administration to consider implementing phase 2 of the National Highway 1A Bypass Project, through Duc Pho town, Quang Ngai province to ensure traffic safety during this period, but due to the uncertain toll revenue, it is impossible to work with the BOT investor to carry out the expansion during this period.

In 2023, the People's Committee of Quang Ngai province also said that the people's petition to continue investing in the National Highway 1A Bypass Project (Phase II) through Duc Pho town (now Duc Pho town), according to the People's Committee of Quang Ngai province, is not feasible, causing great risks for investors.



Source

Comment (0)

Simple Empty
No data

Same tag

Same category

Fireworks filled the sky to celebrate 50 years of national reunification
50 years of national reunification: The checkered scarf - the immortal symbol of the Southern people
The moment the helicopter squadrons took off
Ho Chi Minh City is bustling with preparations for the "national reunification day"

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product