- On the morning of August 20, in Na Duong commune, the Party Committee of TKV Power Corporation held the inauguration and installation of the Steam Drum Lifting Project of Na Duong II Thermal Power Plant Project. This is a project to welcome the 4th Congress of the Group's Party Committee, term 2025 - 2030.
Attending the program were leaders of the Party Committee of Vietnam National Coal - Mineral Industries Group.
The Na Duong II Thermal Power Plant Project is invested by Electricity Corporation - TKV. With a capacity of 110MW, including 1 unit with a total investment of more than 4,088 billion VND. The project strives to complete and put the plant into commercial operation on September 15, 2026.
According to the plan, in 2025, the contractor set two main milestones: completing the steam drum lifting in August and testing the boiler pressure in December. In particular, the steam drum item is a key equipment, considered the "heart" of the boiler system and is the key highlight of the entire project. With a steam drum weighing 82 tons, a length of 11 meters, and a diameter of 2 meters, the work of lifting the steam drum to the installation position is considered a high-level technical challenge, requiring absolutely precise calculations, carefulness and extensive experience, along with the smooth coordination of many departments from construction, supervision to technical experts.
During the period from March 23 to August 3, 2025, the contractor completed the installation of steel structure floors from the 1st floor to a height of 50m. At the same time, from July 30 to August 12, 2025, the transportation, preparation and lifting of the steam drum were carried out. On August 13, 2025, the static installation of the steam drum was completed, marking the transition from structural erection to electromechanical equipment installation, starting with the boiler system. The project was completed ahead of schedule compared to the original plan.
During the program, delegates performed the ceremony of attaching a signboard to the project to welcome the 4th Party Congress of the Group, term 2025 - 2030.
The completed project demonstrates the spirit of emulation and determination of the Party Committee of the Electricity Corporation - TKV to complete the set goals and tasks, practically welcoming the success of the 4th Congress of the Party Committee of the Vietnam National Coal - Mineral Industries Group, towards the 14th National Congress of the Party.
Source: https://baolangson.vn/khanh-thanh-cong-trinh-chao-mung-dai-hoi-dai-bieu-dang-bo-tap-doan-cong-nghiep-than-va-khoang-san-viet-nam-5056576.html