Image of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage

Báo Tiền PhongBáo Tiền Phong11/07/2024


TPO - After completing all stages, the Bach Dang 2 bridge project across the Dong Nai River has reached the final stage of construction to connect the bridge (also known as closing).

The shape of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage, photo 1

On July 11, a representative of the Binh Duong Province Traffic Construction Investment Project Management Board said that the Bach Dang 2 Bridge project across the Dong Nai River connecting Tan Uyen City (Binh Duong) with Vinh Cuu District (Dong Nai) has reached the final stage of completion.

Image of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage, photo 2

The construction unit is trying to speed up to meet the deadline according to the direction of the Chairman of Binh Duong Provincial People's Committee to complete on September 2.

The shape of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage, photo 3

The construction of the bridge across Dong Nai River (Bach Dang 2 Bridge) has a total investment of over 490 billion VND from the budget of Binh Duong province.

The shape of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage, photo 4

The project is a balanced cantilever prestressed concrete bridge. The total length of the project is about 2.8km, the bridge section across the Dong Nai River is about 410m long, 17m wide with 4 lanes.

The shape of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage, photo 5

Currently, the investor and construction unit of Bach Dang 2 Bridge are focusing on speeding up the progress. Up to now, the construction volume has reached over 85% according to the contract.

The shape of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage, photo 6

According to the reporter's records, the main structure at the construction site is basically complete. On the Dong Nai side, railings and lamp posts are being built; and on the Binh Duong side, the road embankment is being completed.

The shape of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage, photo 7

Bach Dang 2 Bridge project started construction in December 2021. The bridge connects Bach Dang commune (Tan Uyen city, Binh Duong province) and Binh Loi commune (Vinh Cuu district, Dong Nai province).

The shape of the bridge across the river connecting Binh Duong and Dong Nai in the closing stage, photo 8

Location of Bach Dang 2 bridge across Dong Nai river (Photo: Satellite)

Recently, Mr. Vo Van Minh - Chairman of Binh Duong Provincial People's Committee requested relevant units to urgently speed up the progress of key projects in the area. Regarding the project to build Bach Dang 2 Bridge across Dong Nai River, the Chairman of Binh Duong Provincial People's Committee requested units to make efforts to inaugurate the project on September 2.

When completed and put into operation, the project will help increase the ability to transport goods and promote socio-economic development of the two localities.

Set completion time for two projects worth nearly 3,000 billion VND in Binh Duong
Set completion time for two projects worth nearly 3,000 billion VND in Binh Duong

Huong Chi



Source: https://tienphong.vn/hinh-hai-cau-bac-qua-song-noi-binh-duong-va-dong-nai-giai-doan-hop-long-post1653972.tpo

Comment (0)

Simple Empty
No data

Same tag

Same category

Heaven and earth in harmony, happy with the mountains and rivers
Fireworks filled the sky to celebrate 50 years of national reunification
50 years of national reunification: The checkered scarf - the immortal symbol of the Southern people
The moment the helicopter squadrons took off

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product