Removing obstacles in the land clearance of 3 intersections and the Van Ninh expressway overpass

Báo Giao thôngBáo Giao thông23/03/2025

Three overpass and intersection locations are still stuck with site clearance, affecting the progress of the main route of the Van Ninh - Cam Lo expressway project in June 2025. The locality is making efforts to hand over the remaining site in March.


The North-South Expressway project, Van Ninh - Cam Lo section, has a total length of more than 65.5km, of which the section through Quang Binh province is more than 33km, passing through Quang Ninh and Le Thuy districts; the section through Quang Tri province is more than 32.5km, passing through Vinh Linh, Gio Linh and Cam Lo districts.

The project has 2 construction packages, of which construction package XL1 (Km 675+400 - Km 708+350) is located in Quang Binh province, constructed by the joint venture of Truong Thinh Group Joint Stock Company - Truong Son Construction Corporation - Construction Joint Stock Company 368.

Construction package XL2 (Km 708+350 - Km 740+884) is located in Quang Tri province, constructed by a joint venture of Truong Thinh Group Joint Stock Company - Construction Transport Joint Stock Company No. 1 - Railway Construction Corporation Joint Stock Company.

Gỡ vướng mặt bằng 3 nút giao, cầu vượt cao tốc Vạn Ninh - Cam Lộ trong tháng 3- Ảnh 14.

One of the sections of the Van Ninh - Cam Lo expressway project through Quang Tri province has installed median strips, anti-glare nets as well as guardrails on both sides...

According to the Ho Chi Minh Road Project Management Board, the project started on January 1, 2023 and was completed in December 2025 (the adjusted schedule strives to complete in June 2025). The project's construction output to date has reached about 78%.

Currently, contractors are taking advantage of favorable weather to deploy a series of construction projects, organizing construction in "3 shifts, 4 teams", striving to basically complete the main route's traffic on June 30.



Source: https://www.baogiaothong.vn/go-vuong-mat-bang-3-nut-giao-cau-vuot-cao-toc-van-ninh-cam-lo-trong-thang-3-19225032315093979.htm

Comment (0)

Simple Empty
No data
Overview of the first A80 training session at Ba Dinh Square
Lang Son expands international cooperation in preserving cultural heritage
Patriotism in the young way
People joyfully welcome the 80th anniversary of National Day
Vietnam women's team beat Thailand to win bronze medal: Hai Yen, Huynh Nhu, Bich Thuy shine
People flock to Hanoi, immersing themselves in the heroic atmosphere before National Day.
Suggested locations to watch the parade on National Day September 2
Visit Nha Xa silk village
See beautiful photos taken by flycam by photographer Hoang Le Giang
When young people tell patriotic stories through fashion

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product