On the afternoon of August 14, comrade Nguyen Hung Nam, Vice Chairman of the Provincial People's Committee inspected the progress of the Tan Phuc - Vong Phan road project (assigned to DT.378).
Vice Chairman of the Provincial People's Committee Nguyen Hung Nam inspected the project site.
According to the report, up to now, 170.1/175.6 hectares of land have been cleared, reaching 96.9% of the plan. The construction volume reached about 70.3% of the contract value, including: Excavation 26.52km of various types of foundation, 26.52km of geotextile, 22km of K98 foundation, nearly 15km of C19 asphalt concrete.
Representative of Department of Construction reported on project progress.
Representative of Nguyen Trai commune reported on the progress of site clearance of the project in the area.
Through on-site inspection, the Vice Chairman of the Provincial People's Committee requested localities to urgently stabilize operations under the new government model; mobilize resources, speed up approval of compensation plans, complete legal procedures and deploy resettlement areas. Localities focus on propaganda, mobilization, and creating high consensus among the people. Construction units mobilize maximum machinery, equipment, and human resources, command construction teams to coordinate and speed up the construction progress of sections with available land. Investors strengthen inspection and supervision to ensure the progress and quality of the project.
Pham Dang
Source: https://baohungyen.vn/vice-chairman-of-the-provincial-board-of-nguyen-hung-nam-inspects-the-progress-of-the-tan-phuc-vong-road-project-3183778.html