Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh inspected the progress of Ca Ty River Apartment Project.

On the afternoon of July 14, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh inspected the actual progress of the Ca Ty River Apartment Project in Binh Thuan Ward, Lam Dong Province.

Báo Lâm ĐồngBáo Lâm Đồng14/07/2025

img_8683.jpg
The working delegation of Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh, including representatives of leaders of relevant departments, branches, units, project investors, Provincial People's Committee Office, and local authorities, inspected the actual situation at the Project.

.

img_8666.jpg
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh reviewed the overall project plan.

After the on-site inspection, Vice Chairman of the Provincial People's Committee Nguyen Minh also chaired a meeting to listen to a progress report on the implementation of the Ca Ty River Apartment Project in the past time.

This is an investment project to serve the resettlement needs of households subject to land acquisition and relocation to implement the Ca Ty River Embankment Project (section from Duc Thanh Bridge to Ung Van Khiem Street) and resettlement for other projects to improve the landscape and urban embellishment.

img_8671.jpg
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh (middle) inspects the Ca Ty River Apartment Project

According to the report of the investor representative, the Provincial Management Board of Civil and Industrial Construction Investment Projects, the Ca Ty River Apartment Project has a total investment of nearly 800 billion VND from the local budget, with an implementation period of 3 years from 2023.

Project scale includes: Apartment block (6 blocks 8 floors high/block and auxiliary parts); flower garden, park - trees; traffic roads and related technical infrastructure system; river embankment; overall power supply; leveling; equipment...

img_8705.jpg
Investor representative reports on project implementation status at the meeting

In the past time, the investor has completed 41 bid packages and passed the bidding process.

Currently, the project only has 2 equipment packages that have not been implemented (tables, chairs, elevators, cameras and wastewater treatment systems). At the same time, many construction and equipment supply packages are under construction, with the possibility of completion in the second half of 2025 and in 2026.

img_8711.jpg
Representatives of relevant departments and branches participated in giving opinions.

Regarding capital disbursement, by the end of June, more than 237.7 billion VND had been disbursed; it is expected that 100% of the 2025 capital plan will be disbursed by the end of December...

With the above implementation status, representatives of relevant departments, branches, units, localities and investors also discussed and proposed solutions to some difficulties and problems in the project construction process, especially in the work of document appraisal, compensation and site clearance, resettlement arrangement as well as other tasks that continue to be focused on implementation...

img_8693.jpg
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh delivered a concluding speech at the meeting.

Through on-site inspection and listening to the report at the meeting, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh acknowledged the efforts of the investor, departments, branches, units and localities in ensuring the project's construction progress.

In the coming time, the provincial leaders require relevant parties to review the work that has been done or not done, actively coordinate to review the legality of documents serving the project's site clearance work. In addition, they also evaluate the feasibility of all items to have an adjustment plan to suit the current reality, aiming to ensure the effectiveness of this project.

In addition, the provincial leaders also requested to urgently complete the project's Compensation, Support and Resettlement Council, continue to urge contractors to speed up the implementation progress, ensuring that the progress must exceed or equal the time according to the signed contract.

On the other hand, research regulations and policies on compensation and site clearance for project implementation to apply to households whose land is subject to land acquisition to ensure a life equal to or better than the old place...

"The spirit is to be extremely proactive in implementing the work," Vice Chairman of the Provincial People's Committee Nguyen Minh requested that relevant parties must perform according to assigned functions and tasks.

Source: https://baolamdong.vn/pho-chu-tich-ubnd-tinh-lam-dong-nguyen-minh-kiem-tra-tien-do-du-an-chung-cu-song-ca-ty-382276.html


Comment (0)

Simple Empty
No data
Overview of the first A80 training session at Ba Dinh Square
Lang Son expands international cooperation in preserving cultural heritage
Patriotism in the young way
People joyfully welcome the 80th anniversary of National Day
Vietnam women's team beat Thailand to win bronze medal: Hai Yen, Huynh Nhu, Bich Thuy shine
People flock to Hanoi, immersing themselves in the heroic atmosphere before National Day.
Suggested locations to watch the parade on National Day September 2
Visit Nha Xa silk village
See beautiful photos taken by flycam by photographer Hoang Le Giang
When young people tell patriotic stories through fashion

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product