Total effort to drill a tunnel through the mountain connecting Ha Tinh - Quang Tri

TPO - After a period of construction, the Deo Ngang tunnel connecting Ha Tinh and Quang Tri with a length of 555m is almost open. The investor and the project implementation unit are making efforts to complete and put the project into use on schedule.

Báo Tiền PhongBáo Tiền Phong16/07/2025

Close-up of the construction of Deo Ngang tunnel connecting Ha Tinh - Quang Tri. Video : Pham Truong.
1.jpg
These days, engineers and workers are divided into many construction teams to "work together" to implement the items of the Deo Ngang road tunnel expansion project. Construction is carried out simultaneously at both the South and North tunnel entrances.
tp-7.jpg
According to the construction unit representative, up to now, the unit has drilled about 550m, and the remaining 5m will be cleared in the coming days.
tp-13.jpg
According to records, at the northern tunnel entrance in Hoanh Son ward ( Ha Tinh ), after drilling and removing soil and rock, the tunnel shell was reinforced with a steel reinforcement system and concrete spraying.
14.jpg
Robots pump concrete onto the roof of the tunnel for reinforcement.
tp-15.jpg
The contractor plans to drill through the Deo Ngang tunnel in the next few days. To ensure safety during construction in an environment with little air, workers are equipped with protective equipment, including gas masks.

5.jpg
Meanwhile, at the southern tunnel entrance in Phu Trach commune ( Quang Tri province), the project implementation unit is also actively removing the last amount of soil and rock to soon complete the tunnel drilling.
tp-6.jpg
The outside of the tunnel is covered with tarpaulin and firmly reinforced to prevent landslides.
11.jpg
Along with the construction of Deo Ngang tunnel, the contractor is also implementing the bridge and access road projects in parallel.
tp-10.jpg
Dong Bo Bridge in the North of Deo Ngang Tunnel has nearly completed 28 bored piles, completed the construction of M2 pier, T3 pier and is continuing with T2 pier, producing Super T girders. Dong Muoi Bridge is digging the foundation pits for M1 and M2 pier. The road section in the North in Ha Tinh province has completed the stone foundation, the South in Quang Tri province is digging the foundation and installing the drainage system along the route.

tp-16.jpg
The new Deo Ngang Tunnel is one of the projects included in the project to upgrade and expand a number of bridges and tunnels on National Highway 1 with a total investment of nearly VND 2,000 billion approved by the Ministry of Construction at the end of December 2023. In particular, the Deo Ngang road tunnel and more than 2km of access road to the tunnel have a construction value of more than VND 340 billion.
101001.jpg
The new tunnel is 555m long and 10.5m wide. When completed, Deo Ngang tunnel will operate 2 parallel tunnels with a roadbed width of up to 20.5m, providing 4 lanes for motor vehicles and 2 lanes for non-motorized vehicles.

Overview of the construction of the billion-dollar underpass on Ring Road 3.5 with Thang Long Avenue

Overview of the construction of the billion-dollar underpass on Ring Road 3.5 with Thang Long Avenue

Feasibility study of tunnel project through Da Nang airport

Feasibility study of tunnel project through Da Nang airport

How is the Giai Phong - Kim Dong underpass construction going after the fence expansion?

How is the Giai Phong - Kim Dong underpass construction going after the fence expansion?

Source: https://tienphong.vn/doc-tong-luc-khoan-ham-xuyen-nui-noi-ha-tinh-quang-tri-post1760200.tpo


Comment (0)

Simple Empty
No data

Same tag

Same category

Inside the exhibition venue for the 80th anniversary of National Day, September 2nd
Overview of the first A80 training session at Ba Dinh Square
Lang Son expands international cooperation in preserving cultural heritage
Patriotism in the young way

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product