Today (March 13), Mr. Luong Minh Phuc - Director of the Management Board of Investment and Construction of Traffic Works of Ho Chi Minh City (Traffic Board) said that the Board will hold the groundbreaking ceremony of phase 3 of the My Thuy intersection project, Thu Duc City tomorrow morning (March 14).

In this phase, the investor will carry out the construction packages of the overpass on Ring Road 2 - right branch with a scale of 4 lanes, and at the same time build the Ky Ha 3 bridge - right branch with the same scale of 4 lanes. The investment level is 312 billion VND, expected to be completed in April 2026.

w nut giao my thuy 18 478 1281.jpg
Phase 3 of the My Thuy intersection project has an investment of 312 billion VND. Photo: Nguyen Hue.

My Thuy intersection is an important connection point on the Dong Van Cong - Vo Chi Cong - Nguyen Thi Dinh axis. This is the gateway to Cat Lai port with the largest cargo volume in the country, often seriously congested and a 'black spot' for traffic accidents.

In 2016, Ho Chi Minh City started the My Thuy intersection project with a total investment of 3,450 billion VND, divided into 2 component project packages.

In which, the construction project has a total investment of 1,826 billion VND divided into 3 investment phases (in which the items of phase 3 have a total investment of 312 billion VND).

The compensation, site clearance and resettlement project has a total investment of 1,623 billion VND, invested by the Thu Duc City Construction Investment Project Management Board.

z6402361891080_e890d28d533e05c00e8075fd17ca03ac.jpg
My Thuy intersection, when phase 3 is completed, will have a scale of 3 floors. Photo: Ho Chi Minh City Traffic Department.

According to Mr. Luong Minh Phuc, up to now, the project has completed a number of items in phase 1 and 2, put into operation from 2019 to 2021 including: Ky Ha 3 Bridge (left branch); left turn underpass from Ring Road 2 to Cat Lai port; overpass on Ring Road 2 (left branch); My Thuy 3 Bridge.

From the end of 2023, the unit will also carry out construction of items such as the left-turn overpass from Cat Lai to Phu My and Ky Ha 4 bridge. However, the project progress is still facing many difficulties due to the incomplete site clearance work.

According to the Traffic Department, the total land area used for the project, compensation, support and resettlement is 16.6 hectares, with 195 households subject to land handover. However, by the end of January 2025, Thu Duc City had only handed over 9/195 cases, affecting the overall progress.

z6402361908129_dcbf02c43289f0189d0306ec17909019.jpg
The Phu My Interchange construction project, when completed, is expected to resolve traffic congestion in the Cat Lai port area and the eastern gateway of Ho Chi Minh City. Photo: Ho Chi Minh City Traffic Department.

This Committee recommends that the People's Committee of Thu Duc City urgently complete site clearance work, ensuring 100% handover of the site before April 30, 2025 to ensure the completion of the entire project in April 2026.

Construction of a 3-level intersection worth over 3,400 billion VND has begun to ease traffic congestion in the East of Ho Chi Minh City.

Construction of a 3-level intersection worth over 3,400 billion VND has begun to ease traffic congestion in the East of Ho Chi Minh City.

The An Phu traffic intersection has a scale of 3 floors with a cost of 3,408 billion VND, expected to be completed in 2025, helping to relieve traffic congestion in the East of Ho Chi Minh City.
Current status of construction of 3,400 billion VND three-level intersection at the gateway to Ho Chi Minh City

Current status of construction of 3,400 billion VND three-level intersection at the gateway to Ho Chi Minh City

After nearly a year and a half of construction, the An Phu intersection project with a budget of more than 3,400 billion VND has emerged and is accelerating to complete on schedule, helping to relieve traffic congestion at the eastern gateway of Ho Chi Minh City.
Ho Chi Minh City: Speeding up the progress of My Thuy intersection project, solving traffic jam 'black spots'

Ho Chi Minh City: Speeding up the progress of My Thuy intersection project, solving traffic jam 'black spots'

To reduce traffic congestion and accidents in the eastern gateway area of ​​Ho Chi Minh City, the Department of Transport has deployed and accelerated the construction progress of the My Thuy traffic intersection project (Thu Duc City).