Troubleshooting completed, Unit 1

Việt NamViệt Nam12/08/2023

After troubleshooting, at 8:56 a.m. on August 12, Unit 1 of Vung Ang 1 Thermal Power Plant ( Ha Tinh Oil and Gas Power Company) officially reconnected to the national grid after nearly 2 years of inactivity.

In September 2021, Unit 1 of Vung Ang 1 Thermal Power Plant (Ky Loi Commune, Ky Anh Town) encountered a technical problem and had to temporarily stop operating.

After the problem was fixed, Unit 1 - Vung Ang 1 Thermal Power Plant reconnected to the national grid.

After many efforts, the technical problem at Unit 1 of Vung Ang 1 Thermal Power Plant has been successfully resolved.

With timely and effective direction from Vietnam Oil and Gas Power Corporation, Ha Tinh Oil and Gas Power Company has implemented periodic repair work combined with troubleshooting and repairing unit 1 to ensure proper technical standards.

After the problem was fixed, Unit 1 - Vung Ang 1 Thermal Power Plant reconnected to the national grid.

Leaders of Vietnam Oil and Gas Power Corporation promptly directed and encouraged officers and workers of Ha Tinh Oil and Gas Power Company to successfully bring Unit 1 back into the grid.

On August 12, 2023, leaders of Vietnam Oil and Gas Power Corporation and contractor leaders came to direct and encourage officers and workers of Ha Tinh Oil and Gas Power Company and contractors at the important moment - bringing Unit 1 of Vung Ang 1 Thermal Power Plant back to the grid.

After the problem was fixed, Unit 1 - Vung Ang 1 Thermal Power Plant reconnected to the national grid.

At 8:56 a.m. on August 12, 2023, Unit 1 of Vung Ang 1 Thermal Power Plant officially reconnected to the national grid.

Mr. Tran Van Tinh - Deputy Director of Ha Tinh Oil and Gas Power Company excitedly said: "After many efforts, at 8:56 a.m. on August 12, 2023, Unit 1 of Vung Ang 1 Thermal Power Plant was officially connected to the national grid. Putting Unit 1 back into operation is of great significance in ensuring national energy security, serving the development of the country's economy ".

After the problem was fixed, Unit 1 - Vung Ang 1 Thermal Power Plant reconnected to the national grid.

Putting Unit 1 back into operation is of great significance in ensuring national energy security.

In the coming time, Ha Tinh Oil and Gas Power Company will focus on operating the factory safely and effectively, completing the assigned production and business plan.

At the same time, choose long-term strategies and solutions to ensure adequate coal supply to meet the plant's operational needs; proactively carry out maintenance and repair of equipment systems, improve the availability of generators, etc.

Thu Phuong


Source

Comment (0)

Simple Empty
No data

Same tag

Same category

Impressive moments of the flight formation on duty at the A80 Ceremony
More than 30 military aircraft perform for the first time at Ba Dinh Square
A80 - Rekindling a proud tradition
The secret behind the nearly 20kg trumpets of the female military band

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product