On August 8, Mr. Ta Gia Manh Hung - Project Executive Director ( Ho Chi Minh Road Project Management Board) said that the entire main road surface will be paved this week. The remaining work such as installing signs, median strips, anti-glare nets, guardrails, road painting... is being carried out in 3 consecutive shifts.
Along with the main route, a service road of more than 20km is also being built, ensuring connectivity and serving people's travel.
When fully completed in November 2025, the Hoa Lien - Tuy Loan expressway will connect the expressway network from Quang Tri to Quang Ngai, creating momentum for the development of the Northwest region of Da Nang , connecting industrial parks, Lien Chieu port and ecological urban areas.