Ho Chi Minh City submits to the Prime Minister a plan to remove obstacles to the 10,000 billion VND flood prevention project

Báo Đầu tưBáo Đầu tư27/09/2024


Ho Chi Minh City submits to the Prime Minister a plan to remove obstacles to the 10,000 billion VND flood prevention project

The Ho Chi Minh City People's Committee proposed that the Government allow the City to adjust the Tidal Flooding Solution Project in Ho Chi Minh City area taking into account climate change factors (phase 1) to construct the remaining part.

On September 24, Chairman of the Ho Chi Minh City People's Committee Phan Van Mai signed document No. 271/BC-UBND proposing to the Prime Minister a plan to remove obstacles in the Project to Solve Flooding Due to Tides in Ho Chi Minh City Area Considering Climate Change Factors - Phase 1 (also known as the 10,000 Billion VND Flood Prevention Project).

According to the Ho Chi Minh City People's Committee, the project is currently facing difficulties due to lack of funding to complete the remaining part of the project.

The reason is that BIDV Bank did not sign the credit contract appendix with Trung Nam BT 1547 Company Limited. Therefore, it is not possible to submit to the State Bank of Vietnam to extend the refinancing disbursement time.

The project to solve tidal flooding in Ho Chi Minh City area takes into account climate change factors, phase I has stopped construction since 2020 until now due to unpaid BT land fund - Photo: TN

To have capital to continue the construction, the Ho Chi Minh City People's Committee once proposed that the Government's Working Group unify the plan and consider submitting it to the Government for approval to entrust the City with the budget to the City State Financial Investment Company (HFIC) . From there, HFIC lent the investor to complete the project because the progress has now reached more than 90%.

However, the Ministry of Finance commented that the proposed plan of Ho Chi Minh City is not suitable because the State Budget Law 2015 does not have regulations on the use of local budget capital to entrust HFIC so that this fund can lend to investors to implement the project.

The next difficulty is that there is no basis for payment of BT contracts because current regulations are not unified, leading to legal problems in adjusting the project.

Therefore, the Ho Chi Minh City People's Committee proposed a solution to allow the City to adjust the project because the total investment of the project has changed, the project implementation time has expired, and there are some shortcomings in the contract signing and implementation.

Because project adjustment takes a long time, the Ho Chi Minh City People's Committee proposed to simultaneously carry out procedures to adjust the project implementation time as a basis for signing the BT Contract Appendix to change the payment method.

After adjusting the BT Contract Appendix, the project basically overcomes the shortcomings stated in Article 1 of Resolution No. 40/NQ-CP dated April 1, 2021.

This is the basis for the City to start making payments using land funds, which are the land plots identified in the BT Contract according to current regulations, to solve the capital source for the Investor to construct the remaining part of the project and reduce the cost of interest incurred while waiting for the completion of project adjustment procedures.

The project to solve tidal flooding in Ho Chi Minh City, phase I (total investment of nearly 10,000 billion VND), started in mid-2016 and is expected to be completed in 2018.

However, after many extensions, the project has not yet determined its final completion date. According to the investor's report, due to the extension of the implementation period, the project incurred interest expenses and other costs, leading to the total investment of the project increasing from VND 9,976 billion to VND 14,398 billion.



Source: https://baodautu.vn/tphcm-trinh-thu-tuong-phuong-an-go-vuong-du-an-chong-ngap-10000-ty-dong-d225853.html

Comment (0)

Simple Empty
No data

Same tag

Same category

Fireworks filled the sky to celebrate 50 years of national reunification
50 years of national reunification: The checkered scarf - the immortal symbol of the Southern people
The moment the helicopter squadrons took off
Ho Chi Minh City is bustling with preparations for the "national reunification day"

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product