An official from the Hanoi Traffic Construction Investment Project Management Board (the investor) said that up to now, the contractor has completed the structure of the lower part of the C-shaped overpass, including many abutments and pillars. 9/9 steel girder structure spans have been erected; concrete has been poured on the bridge deck, and embankments and railings are being erected.
Overview of the C-shaped overpass at present
According to the plan, the concrete of the entire bridge deck is expected to be completed in May. In June, the embankment, steel railings, traffic lighting, and drainage on the bridge will be completed; the asphalt concrete pavement will be completed. After that, the bridge will be tested for load, and the construction of the curb under the bridge, planting trees in the curb, and the asphalt concrete pavement will be completed. It is expected that on June 25, the traffic organization will be completed and the project will be opened to traffic.
According to Thanh Nien , the shape of this bridge has been revealed. On both sides of the bridge, workers are gradually removing the corrugated iron fences and completing the final items.
The C-shaped overpass was built from Pham Ngoc Thach Street to Chua Boc Street, with a total investment of 147.28 billion VND. The bridge has a steel box girder structure with a reinforced concrete slab, more than 320 m long.
The project is being implemented with the aim of improving traffic capacity at the Chua Boc - Pham Ngoc Thach - Ton That Tung - Dong Tac intersection (Dong Da District). This is a route that often experiences traffic congestion. The project has been under construction since October 2021, by a consortium of contractors including Thanh Long Group Joint Stock Company, Cienco1, and Viet Hung Technical Construction Joint Stock Company. However, due to many difficulties during the construction process, the project has been delayed 3 times.
The bridge surface is being completed.
C-shaped overpass section passing through Pham Ngoc Thach - Chua Boc intersection
The C-shaped overpass has a total investment of 147.28 billion VND.
Workers remove corrugated iron barriers at the section passing through Chua Boc street.
Bridge foot waiting for concrete pouring
The bridge has a reinforced concrete slab composite steel box girder bridge span structure, steel girder height 1.2 m
Workers are installing railings for the bridge.
The C-shaped bridge construction area is still congested during rush hour.