Vietnam.vn - Nền tảng quảng bá Việt Nam

Độc lập - Tự do - Hạnh phúc

Hanoi is about to inaugurate two central hospitals with an investment of more than 1,800 billion VND.

After more than 2 years of construction, the Central Maternity Hospital and the Central Children's Hospital, branch 2, have been completed and are ready for the inauguration ceremony to celebrate the 80th anniversary of the August Revolution and National Day, September 2, tomorrow morning, August 19.

Báo Tuổi TrẻBáo Tuổi Trẻ18/08/2025

bệnh viện - Ảnh 1.

Central Maternity Hospital, branch 2 will be inaugurated on August 19 - Photo: BVCC

According to information from the Ministry of Health , the second facility of the Central Maternity Hospital was invested with a total cost of about 950 billion VND, built on a land area of nearly 60,000m², of which the construction area is more than 8,400m². The project consists of 6 floors above ground, 1 technical floor and 1 attic floor, designed in a modern style.

According to the plan, the hospital has a scale of 300 inpatient beds, receiving about 1,000 visits per day. The professional organization at facility 2 includes 11 clinical departments, 4 paraclinical departments, and many supporting functional departments such as coordination room, customer care, pharmacy, pharmaceutical warehouse, technical logistics, etc.

The hospital is designed to serve both long-term inpatient needs and high-quality outpatient care.

bệnh viện - Ảnh 2.

Central Maternity Hospital, branch 2, was invested with a total cost of about 950 billion VND, built on a land area of nearly 60,000m² - Photo: BVCC

Overall, the project has a modern, environmentally friendly architecture. Medical equipment has been invested synchronously from diagnosis, treatment to recovery, and medical staff has been transferred and arranged reasonably.

At the National Children's Hospital, branch 2, the system of modern medical equipment and machinery in departments and rooms is ready for operation.

Many leading advanced equipment in the field of pediatrics such as: testing systems, diagnostic imaging, emergency resuscitation, operating room systems... have been tested, ensuring full compliance with technical and professional safety requirements as prescribed by the Ministry of Health.

bệnh viện - Ảnh 3.

National Children's Hospital, branch 2, with a total investment of 880 billion VND - Photo: BVCC

The second facility of the National Children's Hospital has been invested with more than 880 billion VND, with a total land area of about 6 hectares. Of which, the construction area is about 7,530m2 , including 1 administrative block, 1 paraclinical block, 2 inpatient treatment blocks with 5 floors, 1 basement, and accompanying synchronous technical infrastructure items.

Facility 2 is organized with 11 clinical departments, 4 paraclinical departments and 1 functional unit, ensuring full implementation of emergency, medical examination and treatment and rehabilitation tasks for children. 300 inpatient beds are scientifically arranged... All essential medicines and medical supplies have been stocked, arranged and preserved in accordance with regulations.

Leading experts and doctors from facility 1 will take turns working at facility 2.

The second facility of the two central hospitals coming into operation is expected to reduce the load on the first facility in the inner city, which has been constantly overloaded.

WILLOW

Source: https://tuoitre.vn/ha-noi-sap-khanh-thanh-hai-benh-vien-trung-uong-co-muc-dau-tu-hon-1-800-20250818143727218.htm


Comment (0)

Simple Empty
No data
Inside the exhibition venue for the 80th anniversary of National Day, September 2nd
Overview of the first A80 training session at Ba Dinh Square
Lang Son expands international cooperation in preserving cultural heritage
Patriotism in the young way

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product