The Cai River Road project from Ha Huy Giap Street to Tran Quoc Toan Street is behind schedule due to problems in site clearance. Photo: Pham Tung |
Mr. Ngo Duc Thang, Deputy Director of the Department of Finance, was assigned to be the Head of Working Group No. 2; Deputy Head of Working Group No. 2 is Mr. Mai Phong Phu, Deputy Director in charge of the Provincial Land Fund Development Center.
Members of the two working groups include: representatives of provincial departments and branches; regional project management boards; branches of land fund development centers and chairmen of the People's Committees of wards and communes where the project is to carry out site clearance.
The Provincial People's Committee assigned Working Group No. 1 to be responsible for resolving difficulties and problems in the process of implementing compensation, support and resettlement for projects in the former Binh Phuoc province; Working Group No. 2 to be responsible for resolving difficulties and problems in the process of implementing compensation, support and resettlement for projects in the former Dong Nai province.
The working groups are responsible for proposing and advising the Chairman of Dong Nai Provincial People's Committee on solutions to promptly direct the settlement of tasks and tasks in the areas under the state management scope in the implementation of compensation, support and resettlement of projects under the 2025 public investment plan in the province, in order to promptly hand over the site to investors to implement the project. At the same time, propose solutions to effectively direct and support relevant units to speed up the implementation of legal procedures, remove difficulties, and resolve related issues to promptly implement compensation, support and resettlement to implement projects under the 2025 public investment plan.
The Provincial Road 25B Upgrade Project is still facing difficulties in site clearance. Photo courtesy |
According to the assessment, the disbursement of public investment capital in the province in the first 7 months of 2025 has had positive changes, the disbursement rate is higher than the same period in 2024, but still does not meet the expectations set by the province. One of the reasons for the low disbursement rate of public investment capital is due to difficulties in site clearance.
Pham Tung