As soon as the site is available, the construction unit speeds up the progress. |
The route is designed with a 9m wide roadbed, 8m wide road surface, drainage system, and complete traffic safety system. The project is invested by the Thai Nguyen Province Traffic and Agricultural Construction Investment Project Management Board, with a total investment of over 291 billion VND.
To speed up the construction progress of the road, the investor has coordinated with local authorities to promote propaganda, compensation, site clearance and resettlement. Up to now, the cleared area is 20.35ha/20.83ha, reaching more than 97%; the relocation of medium and low voltage power lines has been completed. The total cost of compensation for site clearance is nearly 35 billion VND.
Regarding the construction progress of the items: The roadbed construction has reached 16% of the volume; the Rong River bridge has reached 19% of the volume; other items (drainage system, traffic safety...) have reached 12% of the volume. The progress milestone is to be completed before December 31, 2025. Regarding the disbursement of the capital plan in 2025, the disbursement value on the allocated capital value reaches over 87/107 billion VND, equal to more than 81%.
The completed route will contribute to enhancing traffic connections between Thai Nguyen and Bac Ninh provinces, promoting the circulation of goods and socio -economic development. In particular, about 400 workers in Dan Tien and Vo Nhai communes... will have more convenience in going to work in industrial parks in Bac Ninh province and the south of Thai Nguyen province.
Source: https://baothainguyen.vn/giao-thong/202508/day-nhanh-tien-do-thi-cong-duong-ket-noi-dt265-di-yen-the-bac-ninh-11653ce/