Vietnam.vn - Nền tảng quảng bá Việt Nam

Độc lập - Tự do - Hạnh phúc

More than 220km of the North-South Expressway component project opened to traffic on August 19

The component projects of the North-South Expressway in the Eastern region in the 2021-2025 period are being constructed by investors and contractors day and night to strive to complete the route on August 19.

Báo Hà TĩnhBáo Hà Tĩnh12/08/2025

Có hơn 220km Dự án thành phần cao tốc Bắc-Nam được thông tuyến dịp 19/8. (Ảnh: Quốc Khánh/Vietnam+)
More than 220km of the North-South Expressway component project was opened to traffic on August 19. (Photo: Quoc Khanh/Vietnam+)

Investors and contractors of the Quang Ngai-Hoai Nhon, Hoai Nhon-Quy Nhon and Quy Nhon-Chi Thanh expressways are focusing on completing the final items to open to traffic on August 19, in accordance with the direction of the Prime Minister and the Ministry of Construction .

Total effort to bring 3 expressway sections to the finish line

The Quang Ngai - Hoai Nhon component project has a route length of 88km. To ensure the first technical traffic opening of the last 10km of the route (from Km79-Km88) connecting to the Hoai Nhon - Quy Nhon expressway on August 19, the contractor Deo Ca Group and the consortium have focused maximum personnel, equipment, and materials to the construction site to construct the remaining items.

The 10km section of the Quang Ngai-Hoai Nhon expressway, which is about to open to traffic, is located entirely in Gia Lai province, in the areas of Bong Son-Hoai Nhon Nam and Hoai Nhon Tay wards, intersecting with the Provincial Road 639 intersection connecting to the Hoai Nhon-Quy Nhon expressway.

Along this section of the route, the road has been paved with smooth asphalt. Contractors are rushing to complete the traffic safety system. Hard dividers are cast right at the yards near the construction site for easy transportation, significantly shortening construction time. Groups of workers install guardrails, anti-glare nets and signs.

Regarding the Hoai Nhon-Quy Nhon Expressway Project with a total length of 70.1km, Mr. Bui Trong Lai, Director of the Project Management Board, said that Package 12-XL (Km23+500-Km70+091) is also nearly completed to open 46.6km of traffic on this August 19th.

According to Mr. Lai, up to now, Package 12-XL has achieved 91.1% output, meeting the approved schedule, and has basically completed the bridge, culvert, and underpass works on the route and the roadbed and surface items, and has constructed most of the traffic safety items including: 38.87/46.59km of fences (93.43%); 39.11/44.11km of guardrails (88.6%), 36.94/46.59km of median strip (79.29%); and road markings.

Công nhân lắp đặt dải phân cách và lưới chống chói tại Dự án cao tốc Quảng Ngãi-Hoài Nhơn. (Ảnh: Quốc Khánh/Vietnam+)

Workers install median strips and anti-glare nets at the Quang Ngai-Hoai Nhon Expressway Project. (Photo: Quoc Khanh/Vietnam+)

In the Quy Nhon-Chi Thanh Expressway Project, 61.7km long, according to the report of Project Management Board 85 (investor), Package 11-XL (Km0+200-Km19+800) with a length of 19.6km has been implemented since February 25, 2023 and has reached 91% completion. According to the plan, this package will be technically opened to traffic on August 19.

Hoa Lien-Tuy Loan Expressway Project Ensures Technical Traffic Opening on August 19

The Hoa Lien-Tuy Loan expressway project is being constructed by the investor and contractor in "3 shifts, 4 crews", urgently completing to ensure technical traffic opening on August 19.

Currently, the consortium of contractors TAG Vietnam Group Joint Stock Company, Construction Corporation No. 1, Railway Construction Corporation Joint Stock Company, Song Da 10 Joint Stock Company, and Construction Service and Trade Joint Stock Company 68 are urgently completing the items for the package to reach the finish line.

Specifically, the contractor is laying asphalt concrete over 3km long, expected to be completed on August 12-13, and is also completing the traffic safety system such as road markings, signs, corrugated iron guardrails, median strips, etc.

Son Trieu Tunnel has also completed the left tunnel (600m long), the right tunnel (535m) reaching 100%; completed the road surface in the tunnel; is implementing the finishing work, installing equipment, lighting, and the operator house....

More than 221km of highway open

With only one week left until the technical opening, Mr. Bui Trong Lai, Executive Director of the Quy Nhon-Chi Thanh Expressway Project, said that at the construction site, contractors have mobilized 246 machines and equipment, 726 construction workers to serve 28 construction teams including 4 tunnel construction teams, 11 roadbed construction teams and 13 bridge construction teams.

“Taking advantage of favorable weather, contractors have increased their construction workforce to work in “3 shifts, 4 teams” to ensure progress. The consulting and supervision team is always there to guide and evaluate the quality of each construction item. Project Management Board 85 also requires contractors to make great efforts and determination to complete the package in time for technical traffic opening on August 19,” Mr. Lai affirmed.

Các dự án thành phần cao tốc Bắc-Nam sẽ được thông xe vào dịp 19/8 tới. (Ảnh: Quốc Khánh/Vietnam+)

The North-South Expressway component projects will be opened to traffic on August 19. (Photo: Quoc Khanh/Vietnam+)

A representative of the Department of Construction Investment and Management (Ministry of Construction) said that implementing the Prime Minister's direction, in recent days, leaders of the Ministry of Construction and project management boards have been continuously present at the sites of expressway projects scheduled to open to traffic on August 19 to directly urge progress and discuss with localities and investors solutions to remove existing obstacles.

According to the report of the Ministry of Construction, by August 19, 7 component projects of the North-South Expressway Project in the East phase 2021-2025 will complete the main route with a total length of more than 221km including: Vung Ang-Bung (55.34km), Van Ninh-Cam Lo (65.55km) and the remaining 13km of the Van Phong-Nha Trang expressway section, some sections of the Quang Ngai-Hoai Nhon section (10/88km), Hoai Nhon-Quy Nhon (46.6/70km), Quy Nhon-Chi Thanh (19.6/62km) and the Hoa Lien-Tuy Loan project (11.47km) will be opened to traffic./.

Source: https://baohatinh.vn/hon-220km-du-an-thanh-phan-cao-toc-bac-nam-duoc-thong-tuyen-dip-198-post293554.html


Comment (0)

Simple Empty
No data
Summary of A80 training: The army marches in the arms of the people
Gen Z's creative and unique way of showing patriotism
Inside the exhibition venue for the 80th anniversary of National Day, September 2nd
Overview of the first A80 training session at Ba Dinh Square

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product