Investing in building and renovating people's court headquarters in 49 provinces and cities

Báo Kinh tế và Đô thịBáo Kinh tế và Đô thị01/01/2025


Illustration
Illustration

The Decision clearly states the investment objective to repair, renovate, upgrade and build new People's Court headquarters to ensure facilities to serve the Court's operations well, meet the requirements of judicial reform, and be suitable to local characteristics.

Accordingly, investment in new construction, renovation and expansion of working headquarters and auxiliary items of provincial and district People's Courts in 49 provinces and cities nationwide, including: 15 projects of provincial People's Court headquarters; 75 projects of district People's Court headquarters.

This is a group A project, invested in the form of public investment. The total estimated investment is about 5,873 billion VND.

The capital structure includes public investment capital from the state budget allocated to the People's Court system and local support capital. The project implementation period is 6 years, expected to start in 2025.

The project is divided into component projects, the basic content of each project is detailed in the Appendix attached to this Decision.

Project implementation ensures quality, on schedule, and prevents negativity and waste.

The Prime Minister assigned the Supreme People's Court to take full responsibility for the information and data in the Project's Pre-Feasibility Study Report, as well as information reported on receiving and explaining opinions of relevant ministries and branches, ensuring the feasibility of the Project.

Organize the assignment of investors to manage the implementation of component projects. Direct and urge investors to coordinate with relevant agencies to develop Feasibility Study Reports of component projects to submit to competent authorities for project approval in accordance with the provisions of the Law on Public Investment and construction laws.

Study and fully absorb the opinions of the Ministry of Planning and Investment in Appraisal Report No. 10626/BC-BKHĐT dated December 23, 2024; direct investors to organize the preparation, appraisal and approval of Environmental Impact Assessment (EIA) Reports during the preparation and appraisal of feasibility study reports and implementation of projects in accordance with regulations.

At the same time, balance and allocate sufficient capital to implement investment in component projects and organize project implementation in accordance with approved planning and regulations of the Law on Public Investment, the Law on Construction and relevant legal regulations, ensuring publicity, transparency, quality, efficiency and progress; absolutely not allowing negativity and waste to occur.

The Ministry of Planning and Investment is responsible for presiding over and coordinating with the Ministry of Finance and the Supreme People's Court to review and balance sufficient capital for the Project within the total state budget for the period 2021 - 2025 and subsequent periods in accordance with the law. Inspect and supervise the implementation of this Decision and report to the Prime Minister in accordance with the law.

The Ministries of Finance, Construction, and Natural Resources and Environment are responsible for coordinating according to their functions and tasks during project implementation.

The People's Committees of provinces and centrally run cities shall coordinate with the Supreme People's Court and relevant agencies in the process of project implementation and be responsible for: Arranging land allocation in accordance with the planning approved by competent authorities. Within the scope of functions and tasks, promptly provide opinions when requested. During the project implementation, direct specialized agencies to quickly and effectively implement the procedures: approval, approval of construction planning adjustment; agreement on infrastructure connection, electricity, water...; environmental impact assessment; appraisal, appraisal of project documents... to ensure project progress. Balancing local budget sources within capacity for compensation, site clearance, clean land allocation and investment funding support.



Source: https://kinhtedothi.vn/dau-tu-xay-moi-cai-tao-tru-so-toa-an-nhan-dan-tai-49-tinh-thanh.html

Comment (0)

Simple Empty
No data

Same tag

Same category

Pilot recounts the moment 'flying over the sea of ​​red flags on April 30, his heart trembled for the Fatherland'
Ho Chi Minh City 50 years after reunification
Heaven and earth in harmony, happy with the mountains and rivers
Fireworks filled the sky to celebrate 50 years of national reunification

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product