Thousands of engineers and workers stick to the construction site, bringing the North-South Expressway to life

Báo Giao thôngBáo Giao thông01/09/2024


Mr. Nguyen Khac Trung, Project Executive Director, said that currently, the project's construction output has reached about 55% of the contract value, the average weekly output is about 80 billion VND, basically meeting the required progress. Of which, hollow asphalt concrete has been constructed for 21/54.2km; C19 dense asphalt concrete has reached 19/54.2km; C16 asphalt concrete has reached 1.5/54.2km. (In the photo: Contractor transporting and constructing the bridge girder).



Source: https://www.baogiaothong.vn/hang-nghin-ky-su-cong-nhan-bam-cong-truong-dua-cao-toc-bac-nam-giai-doan-2-ve-dich-som-192240901153206068.htm

Comment (0)

Simple Empty
No data

Same tag

Same category

Pilot recounts the moment 'flying over the sea of ​​red flags on April 30, his heart trembled for the Fatherland'
Ho Chi Minh City 50 years after reunification
Heaven and earth in harmony, happy with the mountains and rivers
Fireworks filled the sky to celebrate 50 years of national reunification

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product