Chairman of Hanoi People's Committee Tran Sy Thanh has just signed Plan No. 272/KH-UBND on the progress of implementing key projects of the City in the period of 2021-2025.
Accordingly, at the meeting of the City People's Council in July 2023, the adjustment of the progress, list, and capital plan of key projects was approved in Resolution No. 12/NQ-HDND dated July 4, 2023. Accordingly, the total number of key projects of the City in the period of 2021-2025 after adjustment is 42 projects with a total expected investment of VND 353,192 billion in 11 fields.
Of these, 35 projects use budget capital, 1 project is invested in the form of PPP, and 6 projects are invested in the form of socialization.
By October 31, 2023, 2 projects had been completed; 13 investment projects were allocated capital plans for 2023 for implementation; 14 new investment projects had their investment policies approved, but their projects had not been approved; 7 investment projects had been assigned tasks but their investment policies had not been approved; 1 investment project had not been assigned tasks; The implementation of 6 investment projects in the form of socialization was still slow.
From then on, according to the plan, from now until 2025, Hanoi will resolutely deploy, strive to complete and put into operation 16 projects, of which 14 projects use budget capital; 1 project invested in the form of PPP, 1 project invested directly in the form of socialization. At the same time, focus on completing investment procedures, speeding up the implementation of 26 projects according to the plan to be completed after 2025.
Hanoi City issued a plan to speed up the implementation of key projects in the 2021-2025 period (Photo: Huu Thang).
The plan requires units to specify the content of the implementation progress for each work item and capital source in 2023-2025 for each project using budget capital so that the city's agencies and units can implement it according to their assigned functions and tasks, ensuring progress and quality, on target, publicity and transparency.
Thoroughly understanding the investor's ideology, the units participating in project implementation need to identify this as an important political task, need to focus time, intelligence, and arrange human resources to actively and proactively participate with a high sense of responsibility, speeding up the progress of implementing key projects.
Carry out assigned tasks with the ideology of "Promoting pioneering and exemplary responsibilities, the spirit of innovation and creativity, daring to do and taking responsibility for the common interests of cadres and party members, especially leaders and cadres at the grassroots level".
To implement this plan, the Chairman of Hanoi requested relevant departments, branches and units to focus on four tasks and solutions: speeding up administrative procedures, removing difficulties and obstacles for key projects; focusing on mobilizing resources for public investment; focusing on directing drastically to complete site clearance for key projects;
Enhance the responsibility, proactiveness and determination of investors, state agencies managing contracts, agencies assigned to prepare proposal documents, feasibility study reports on investment projects and investors (for investment projects in the form of PPP and socialization) .